Meera Investments Limited has secured a significant advantage in its long-running legal battle with architectural firm FBW (U) Limited after the High Court upheld key findings against the firm while allowing it to temporarily halt execution of a Shs2.7 billion judgment pending an intended appeal.
The ruling, delivered on Friday by High Court Commercial Division Judge Susan Odongo, arose from an application by FBW, Paul Moores and Nigel Tilling seeking to stop execution of a judgment delivered in April in favour of Meera Investments.
Although the court granted FBW a conditional stay, it firmly rejected several of the firm’s arguments challenging the original judgment.
In particular, the court ruled in Meera’s favour on the contentious issue of whether FBW had been properly notified when the judgment was uploaded onto the Electronic Court Case Management Information System (ECCMIS).
FBW argued that it only learnt of the April 3 judgment on May 15 through a lawyers’ social media platform, arguing that the lack of electronic notification caused it to miss the statutory appeal deadline.
Meera, through its director Dr Sudhir Ruparelia, countered that FBW’s lawyers were registered ECCMIS users and had a duty to monitor the system.
Justice Odongo agreed with Meera, holding that the uploading of the judgment on ECCMIS constituted effective legal notice. The court said lawyers had an ongoing professional duty to monitor the electronic court registry.
The court also took a strong position on the substance of FBW’s proposed appeal, describing its challenge to the original judgment as having “zero likelihood of success on its merits”, although it found that the filing of the notice of appeal and related applications was sufficient to establish a prima facie right to appeal.
The original dispute arose from a 2012 consultancy agreement under which FBW was contracted to provide architectural, structural and mechanical/electrical drawings for the expansion of Kabira Country Club.
The project was later suspended and revived, leading to disagreements over payments and the format of drawings supplied by FBW. Meera argued that the firm failed to provide usable editable CAD files and was forced to engage another consultant to redraw the project.
In the April judgment, the court ordered FBW and its associates to refund USD132,750, pay USD108,500 in special damages and USD500,000 in general damages, bringing the principal award to USD741,250, before interest and costs.
While the latest ruling temporarily protects FBW from execution, the court required it to secure the undisputed USD132,750 within 45 days.
FBW must either deposit the money in court or provide an unconditional, irrevocable and on-demand bank guarantee from a reputable Ugandan commercial bank.
Failure to meet the condition will automatically cancel the stay, allowing Meera to proceed with execution of the entire judgment without seeking another court order.
The court said the remaining damages awards were contested and raised triable questions on proof and quantum, making it inequitable to require FBW to secure the entire judgment before pursuing its appeal.
The costs of the stay application will be determined alongside the outcome of FBW’s intended appeal.
For Meera, the ruling therefore preserves the substance of its April victory while allowing the appellate process to proceed. For FBW, the conditional stay provides breathing room to pursue an appeal without facing immediate execution that the court found could cripple its business.




